Project Duration
Stipulated Date of Commencement November 26 2022
Stipulated Date of Completion /
Likely Date of Completion
July 31 2024
Status
90%
Completed
Cost (₹)
Estimated at ₹ 4,256,245.71
Awarded for ₹ 3,833,821.79

Project highlights

Setting up STP and its Electromechanical work

 
Gallery Image
Contractors
M/s. Samco Water Technologies
Gallery Image
Consultants
M/s. FP Project Management
 
Similar Projects

See Similar Projects

Similar Project

Interior & Furniture Works

View Details
Similar Project

Construction of Sainik Aramgarh (Rest House) at Bambolim -Furniture works.

View Details
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the OTIS make 15 passenger cum bed lift installed at TB and Chest Diseases Hospital, St. Inez Goa for a period of three years (2020-2023).

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.