Project Duration
Stipulated Date of Commencement
May 26 2023
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
80%
Completed
Cost (₹)
Estimated at
₹ 66,123,471.69
Awarded for
₹ 61,834,796.70
Project highlights
New building for the CHC with 100 bed capacity
Contractors
M/s. Deshpande Constructions
Consultants
M/s. KICONS Limited
Sub Works
This project involved 5 sub works. The details of the same available below
1
Interior Works
80% Completed
Project Duration
Stipulated Date of Commencement
October 08 2018
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 43,991,163.00
Awarded for
₹ 38,714,576.02
Project highlights
Interior works, false ceiling and miscellaneous works
Contractors
M/s. T. S. Mistry,
Consultants
M/s. KICONS Limited
2
Supply, Installation, Testing & Commissioning of Hospital Furniture.
80% Completed
Project Duration
Stipulated Date of Commencement
January 17 2022
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 10,824,992.64
Awarded for
₹ 9,125,700.00
Project highlights
Hospital furniture works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. KICONS Limited
3
Balance HVAC works.
80% Completed
Project Duration
Stipulated Date of Commencement
June 26 2023
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
70%
Completed
Cost (₹)
Estimated at
₹ 5,232,093.87
Awarded for
₹ 4,843,757.08
Project highlights
HVAC works.
Contractors
M/s Shree Manguirish Air Conditioning Co.
Consultants
M/s. KICONS Limited
4
Balance electrical and LV works
80% Completed
Project Duration
Stipulated Date of Commencement
December 26 2023
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
51%
Completed
Cost (₹)
Estimated at
₹ 26,524,126.58
Awarded for
₹ 28,457,026.40
Project highlights
Electrical and LV works of the building.
Contractors
M/s. Siddharud Electricals
Consultants
M/s. KICONS Limited
5
Balance Fire-fighting works
80% Completed
Project Duration
Stipulated Date of Commencement
February 18 2024
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
19%
Completed
Cost (₹)
Estimated at
₹ 7,252,638.47
Awarded for
₹ 7,816,121.71
Project highlights
Fire-fighting, fire alarm and fire supression system of the building.
Contractors
M/s. Antifire Systems
Consultants
M/s. KICONS Limited
See Similar Projects
Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa SH: CCTV, Audio Visual Conferencing, Queue Management and other allied works
View Details
Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa – Fire escape ramp.
View Details
Supply, Installation, Testing & Commissioning of Hospital Furniture.
View Details