Project Duration
Stipulated Date of Commencement
October 28 2021
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 134,712,342.12
Awarded for
₹ 151,930,381.32
Project highlights
Expansion of existing Primary Health Centre, Sanguem by constructing new 44 bedded Hospital.
Contractors
M/s. DHIPL Projects Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.
View Details
Construction of New Premises for Community Health Centre at Tuem, Pernem, Goa: Balance Civil & Plumbing works.
View Details
Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa SH: CCTV, Audio Visual Conferencing, Queue Management and other allied works
View Details





