Project Duration
Stipulated Date of Commencement October 28 2021
Stipulated Date of Completion /
Likely Date of Completion
July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at ₹ 134,712,342.12
Awarded for ₹ 151,930,381.32

Project highlights

Expansion of existing Primary Health Centre, Sanguem by constructing new 44 bedded Hospital.

 
Gallery Image
Contractors
M/s. DHIPL Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.

View Details
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem, Goa: Balance Civil & Plumbing works.

View Details
Similar Project

Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa SH: CCTV, Audio Visual Conferencing, Queue Management and other allied works

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.