Project Duration
Stipulated Date of Commencement September 22 2015
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
85%
Completed
Cost (₹)
Estimated at ₹ 167,103,404.00
Awarded for ₹ 196,795,091.44

Project highlights

The scope includes renovation of Existing Ravindra Bhavan at Curchorem and Construction of IInd Phase of Ravindra Bhavan which include the following:-
• New auditorium of 200 seats
• Amphitheatre of 2000 Capacity
• Statue of Gurudev Ravindranath Tagore
• Guest Rooms
• Administrative offices & Conference Room
• Sound insulated Musical Classes / Workshops
• Convenience shops
• Utility structures
• Site Development

 
Gallery Image
Contractors
M/s. AYG Realty Pvt. Ltd
Gallery Image
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
 

Sub Works

This project involved 6 sub works. The details of the same available below

1

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Interior and Allied Works

85% Completed
 
Project Duration
Stipulated Date of Commencement March 06 2024
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
20%
Completed
Cost (₹)
Estimated at ₹ 18,534,545.98
Awarded for ₹ 26,275,688.00

Project highlights

The scope of work includes Acoustic Wall panaelling, Acoustic False ceiling, signages, Furniture works, aluminium louvers, etc.

 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
2

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Road and Misc. Works

85% Completed
 
Project Duration
Stipulated Date of Commencement April 18 2022
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at ₹ 11,680,980.00
Awarded for ₹ 12,055,767.00

Project highlights

The scope of work includes construction of Concrete road, laying of pavers, etc.

 
Contractors
Contractors
M/s. A.R. Constructions
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
3

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Stage lighting and Drapery works

85% Completed
 
Project Duration
Stipulated Date of Commencement October 21 2021
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
35%
Completed
Cost (₹)
Estimated at ₹ 4,451,677.00
Awarded for ₹ 3,499,308.00

Project highlights

The scope of work includes stagelighting and drapery system for Auditorium.

 
Contractors
Contractors
M/s. Canara Lighting Industries Pvt. Ltd
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
4

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa .-CCTV works

85% Completed
 
Project Duration
Stipulated Date of Commencement October 29 2021
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
15%
Completed
Cost (₹)
Estimated at ₹ 1,117,943.00
Awarded for ₹ 1,066,970.00

Project highlights

The scope of work includes CCTV cameras for Amphitheatre , Auditorium and Surrounding premises.

 
Contractors
Contractors
M/s. Geeta Automation and Technologies
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
5

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- Audio Video (AV) Works.

85% Completed
 
Project Duration
Stipulated Date of Commencement August 30 2022
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at ₹ 12,340,311.00
Awarded for ₹ 11,927,174.00

Project highlights

Audio Video (AV) Works.

 
Contractors
Contractors
M/s. Pentagon Automation Concepts
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
6

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- 11 KV HT Substation Work.

85% Completed
 
Project Duration
Stipulated Date of Commencement February 26 2024
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
20%
Completed
Cost (₹)
Estimated at ₹ 19,286,229.92
Awarded for ₹ 19,187,318.28

Project highlights

HT Power supply to the premises.

 
Contractors
Contractors
M/s. Siddharud Electricals
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
Similar Projects

See Similar Projects

Similar Project

Construction of Wholesale Fish Market at Margao – Phase II

View Details
Similar Project

Reconstruction of Panchayat Ghar along with commercial shops, hall and other amenities for administrative purpose at Molcornem, Quepem, Goa.

View Details
Similar Project

Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Renovation of Panchayat Farm and Construction of New Tourist Cottages at V. P. Bhironda

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.