Project Duration
Stipulated Date of Commencement
February 10 2023
Actual Date of Completion
August 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,637,094.00
Awarded for
₹ 1,699,807.30
Project highlights
Fire Fighting System works
Contractors
M/s.Fyreguard Enterprises
Consultants
M/s. Ameet Sukhthankar Architects & Interior Designers