Project Duration
Stipulated Date of Commencement January 2 2016
Actual Date of Completion June 30 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 151141272.59
Awarded for ₹ 157912311.00
Final Cost of Project ₹ 107022086.00

Project highlights

The work of Promenade was executed from Youth Hostel to Kala Academy having 900 meter length with 4.5 m wide walkway & 2.5 m cycle track. Rip rap was provided to protect the coast. Selfie points & senior citizen park was renovated.

 
Gallery Image
Contractors
M/s. Krishna Builder
Gallery Image
Consultants
M/s. LKS India Pvt Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Panchayat Complex at Chicalim

View Details
Similar Project

Upgradation of facilities of Pilgrims for Exposition 2014 at Old Goa – Internal works.

View Details
Similar Project

Fire Alarm.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.