Project Duration
Stipulated Date of Commencement July 10 2015
Actual Date of Completion May 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,355,777.00
Awarded for ₹ 4,144,116.80

Project highlights

Construction of Box Culvert Work.

 
Gallery Image
Contractors
M/s.Aashirwad Constructions
Gallery Image
Consultants
M/s.Mahimtura Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of compound wall at Bainguinim for the proposed Municipal Solid Waste Management Facility for the CCP.

View Details
Similar Project

Renovation of Building of Directorate of Higher Education, Porvorim, Goa – Fire Fighting System work.

View Details
Similar Project

Resurfacing of main road from Miramar Circle to NIO Circle for IFFI 2012.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.