Project Duration
Stipulated Date of Commencement
October 31 2022
Actual Date of Completion
November 19 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,193,574.30
Awarded for
₹ 3,354,850.00
Project highlights
The project consists of 11 KV Substation in the Kala Bhavan premises for providing 11 KV HT Power Supply to the building.
Contractors
M/s. Pristine Engg. Services
Consultants
M/s Structwel Designers & Consultant Pv t. Ltd.