Project Duration
Stipulated Date of Commencement
August 11 2014
Actual Date of Completion
July 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,174,032.00
Awarded for
₹ 20,705,433.60
Project highlights
Construction of compound wall for a stretch of 1.87 Km
Contractors
M/s.Race Construction
Consultants
M/s.Bhaskar Wagle & Associates