Project Duration
Stipulated Date of Commencement
January 25 2007
Actual Date of Completion
April 15 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,027,157.00
Awarded for
₹ 49,303,872.49
Contractors
M/s. BGM Consortium Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
Sub Works
This project involved 1 sub works. The details of the same available below
1
Lifts / Elevator work.
100% Completed
Project Duration
Stipulated Date of Commencement
February 19 2010
Actual Date of Completion
October 31 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 691,420.00
Awarded for
₹ 792,560.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Construction of new Government Primary and Secondary Schools in the State of Goa – GHS at Honda, GPS at Bhironda and GHS at Guleli in Sattari taluka.
View Details
Repairs/Upgradation & maintenance of Government SchoolS in State of Goa – Civil, Plumbing & Electrical works – Package B (Quepem Taluka) – GPS Borimal, GPS Gajanan, GPS Chinchnagar, GPS Kamral, GPS Kumbharwada Sirvoi
View Details
Repairs/Upgradation and maintenance of Govt. schools in the State of Goa-Civil, Plumbing and Electrical works -Salcete Taluka-Package B (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda)-4th CALL.
View Details