Project Duration
Stipulated Date of Commencement February 08 2015
Actual Date of Completion March 31 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.19,93,04,971.61
Awarded for ₹ Rs.22,98,73,257.00

Project highlights

The building is G+1 RCC framed structure with a mezzanine floor having a Football ground, which is housed on a net area of 27,473.48 Sqm, with a total built up area of 5,400.20 sqm GROUND FLOOR • Boxing ring with toilet for Ladies & Gents.
• Panchayat Office with Cabin for Sarpanch & Secretary, a Conference Room, Record Room, General Staff and Service room along with toilet facilities.
• Doctor’s & Veterinary Doctor’s Room having individual toilets.
• Post Office, Shops – 13 nos. with common toilet facilities.
• Two Lifts with capacity of 8 passengers in each. FIRST FLOOR :• Badminton Court as per standard size, Reading Room, Gymnasium, Cafeteria with Pantry Room for Indoor Games like Chess, Carrom, etc., Toilet facilities for ladies and gents
• A Multipurpose Hall [with capacity of 300 people] with Green Room for Ladies & Gents along with Mezzanine Floor for Multipurpose Hall having Kitchen, Dining, Kitchen Store & Toilets.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Banaji & Associates
 

Sub Works

This project involved 3 sub works. The details of the same available below

1

Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.

100% Completed
 
Project Duration
Stipulated Date of Commencement February 27 2009
Actual Date of Completion August 09 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,541,225.00
Awarded for ₹ 10,902,411.00

Project highlights

Construction of retaining wall, compound wall and land filling etc.

 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Banaji & Associates
2

Construction of Multipurpose Hall and Office Building for V.P.Salvador Do Mundo – Additional works.

100% Completed
 
Project Duration
Stipulated Date of Commencement March 04 2019
Actual Date of Completion June 30 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,785,068.56
Awarded for ₹ 28,035,272.68

Project highlights

Construction of compound wall, ground & concrete road.

 
Contractors
Contractors
M/s. Gore Infrastructure
Consultants
Consultants
M/s. Banaji & Associates.
3

INTERIOR WORKS

100% Completed
 
Project Duration
Stipulated Date of Commencement December 30 2017
Actual Date of Completion April 30 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.1,17,90,772.00
Awarded for ₹ Rs.1,03,92,743.60

Project highlights

Providing of Office Furniture, Gym equipments, aluminium glazing work, Signages etc.

 
Contractors
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
Consultants
M/s. Banaji & Associates
Similar Projects

See Similar Projects

Similar Project

Completion of balance work of culvert opposite to home science college at Miramar.

View Details
Similar Project

Structural works in Auditorium

View Details
Similar Project

Sound System.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.