Project Duration
Stipulated Date of Commencement
January 23 2019
Actual Date of Completion
June 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,509,004.70
Awarded for
₹ 1,260,000.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of a 5 Passenger lift at the premises.
Contractors
M/s.Omega Elevators
Consultants
M/s. Datta Kare Associates