Project Duration
Stipulated Date of Commencement
June 22 2015
Actual Date of Completion
July 17 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 571,816.35
Awarded for
₹ 654,957.00
Project highlights
Providing 11 KV transformer substation for releasing of electrical power supply to Commercial Tax Office, Ponda .
Contractors
M/s. S. Electricals
Consultants
M/s Saolapurkar & Associates