Project Duration
Stipulated Date of Commencement March 27 2007
Actual Date of Completion May 31 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 203,081,980.00
Awarded for ₹ 228,194,428.00

Project highlights

Science Faculty Building is conceptualized to meet the ever-growing needs of expansion of the campus to incorporate study of Science, for quality research facility and to create an excellent, modern research facility.
The work is completed in all respects at a cost of Rs. 48.00 Crore approximately and inaugurated on 13th May 2013.
The building is basement plus 2 storied RCC framed structure.
The built-up area is 20210.00 Sqm.
The structure is planned with three blocks AB block, C block and DE block, Where C block is joining of two wings AB and DE having main entrance at the Ground floor and Library and offices on upper floors. AB Block and DE block comprises lecture hall, research lab and administration spaces.
The building comprises of two seminar halls. One in AB block having capacity of 180 No chairs and other in DE block having capacity of 325 No chairs.
There are four central open courtyards for natural light and ventilation into the rooms.
The building has six staircase blocks designed for public circulation and one internal staircase in the library. All the staircases are well equipped for fire escape. Also 4 Nos. of lifts are provided.
Building is well equipped with fire fighting equipments, networking facilities, lab furniture, fume hoods in labs, gas piping in labs, interior & acoustic, furniture, etc.
All the floors are provided with adequate toilet facilities, etc.
Parking facilities for four wheelers and two wheelers, RCC road, landscaping, STP & ETP, Gas Bank, Pump room etc.

 
Gallery Image
Contractors
M/s. D. S. Contractors Private Limited
Gallery Image
Consultants
M/s. Effective Architectural Services
 

Sub Works

This project involved 14 sub works. The details of the same available below

1

Lifts / Elevator work.

100% Completed
 
Project Duration
Stipulated Date of Commencement October 05 2009
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,450,000.00
Awarded for ₹ 2,570,000.00
 
Contractors
Contractors
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
2

Structural Steel, Roofing and Structural Glazing works

100% Completed
 
Project Duration
Stipulated Date of Commencement August 14 2010
Actual Date of Completion April 30 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,300,928.00
Awarded for ₹ 16,920,811.16
 
Contractors
Contractors
M/s. D. S. Contractors Private Limited
Consultants
Consultants
M/s. Effective Architectural Services
3

External Electrical work

100% Completed
 
Project Duration
Stipulated Date of Commencement November 27 2010
Actual Date of Completion August 20 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,59,76,814.81
Awarded for ₹ 3,25,13,771.00
 
Contractors
Contractors
M/s. Rohini Industrial Electricals Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
4

Fire Fighting Works

100% Completed
 
Project Duration
Stipulated Date of Commencement January 20 2011
Actual Date of Completion December 31 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,548,704.00
Awarded for ₹ 11,883,785.00
 
Contractors
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Consultants
Consultants
M/s. Effective Architectural Services
5

False ceiling work.

100% Completed
 
Project Duration
Stipulated Date of Commencement February 19 2011
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,123,055.00
Awarded for ₹ 13,112,071.90
 
Contractors
Contractors
M/s. Concept Creators
Consultants
Consultants
M/s. Effective Architectural Services
6

Sewage & Effluent Treatment Plant

100% Completed
 
Project Duration
Stipulated Date of Commencement June 22 2011
Actual Date of Completion September 20 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,648,277.41
Awarded for ₹ 3,589,980.00
 
Contractors
Contractors
M/s. Sombansi Enviro Engg. Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
7

Air conditioning work.

100% Completed
 
Project Duration
Stipulated Date of Commencement April 02 2011
Actual Date of Completion October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 28,636,345.00
Awarded for ₹ 22,999,999.00
 
Contractors
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
8

Lab furniture work

100% Completed
 
Project Duration
Stipulated Date of Commencement December 15 2011
Actual Date of Completion June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 48,287,670.00
Awarded for ₹ 29,652,470.00
 
Contractors
Contractors
M/s. Godrej & Boyce Mfg. Co. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
9

Gas piping work.

100% Completed
 
Project Duration
Stipulated Date of Commencement February 27 2012
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,417,128.15
Awarded for ₹ 20,297,433.80
 
Contractors
Contractors
M/s. Steel Case
Consultants
Consultants
M/s. Effective Architectural Services
10

Fumehood, Blowers and Ducting work

100% Completed
 
Project Duration
Stipulated Date of Commencement April 19 2012
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,214,351.00
Awarded for ₹ 18,028,622.54
 
Contractors
Contractors
M/s. Steel Case
Consultants
Consultants
M/s. Effective Architectural Services
11

Networking work

100% Completed
 
Project Duration
Stipulated Date of Commencement September 19 2012
Actual Date of Completion September 06 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,352,655.95
Awarded for ₹ 7,145,532.34
 
Contractors
Contractors
M/s. GMP Technology Solutions Pvt. Ltd
Consultants
Consultants
M/s. Effective Architectural Services
12

Interior & Acoustic Work

100% Completed
 
Project Duration
Stipulated Date of Commencement December 17 2012
Actual Date of Completion October 21 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 31,641,360.00
Awarded for ₹ 31,593,913.87
 
Contractors
Contractors
M/s. T. S. Mistry
Consultants
Consultants
M/s. Effective Architectural Services
13

Lab Accessories work.

100% Completed
 
Project Duration
Stipulated Date of Commencement January 13 2013
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,67,16,761.10
Awarded for ₹ 1,64,23,070.00
 
Contractors
Contractors
M/s. Steel Case
Consultants
Consultants
M/s. Effective Architectural Services
14

Bio Incubator : Civil & Plumbing works.

100% Completed
 
Project Duration
Stipulated Date of Commencement October 09 2012
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,016,258.00
Awarded for ₹ 13,083,870.45

Project highlights

Foreclosed.
GSIDC in its 124th Board Meeting held on 28th November 2013, vide Resolution No.3367, resolved to foreclose the Contract of M/s. Indiana Build Infrastructure Pvt. Ltd.

 
Contractors
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
Similar Projects

See Similar Projects

Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim- Goa. Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works

View Details
Similar Project

Painting and other ancillary works along major internal roads of Panaji city

View Details
Similar Project

Interior & furniture works.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.