Project Duration
Stipulated Date of Commencement October 18 2014
Actual Date of Completion March 31 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 715,187,923.00
Awarded for ₹ 798,752,662.22

Project highlights

New building for the High Court bench of Bombay at Goa.

 
Gallery Image
Contractors
M/s. M Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s LKS India Pvt. Ltd.
 

Sub Works

This project involved 6 sub works. The details of the same available below

1

False ceiling, interior, furniture, signage, security installation and other miscellaneous works.

100% Completed
 
Project Duration
Stipulated Date of Commencement July 15 2019
Actual Date of Completion April 30 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 221,496,176.00
Awarded for ₹ 204,287,929.54

Project highlights

False ceiling, interior, furniture signage, security installation and other miscellaneous works. Interior works for the new High Court building includes false ceilings, furniture, signages etc.

 
Contractors
Contractors
M/s. Siddhi Construction,
Consultants
Consultants
2

Landscaping, Civil, Land Development, Outdoor Lighting and other allied works

100% Completed
 
Project Duration
Stipulated Date of Commencement February 17 2020
Actual Date of Completion September 30 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 139,113,400.00
Awarded for ₹ 133,903,958.00

Project highlights

Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to lands

 
Contractors
Contractors
M/s. Bagkiya Constructions Private Limited
Consultants
Consultants
3

Supply and laying of 33KV HT cable from Sai service junction to the new High Court Complex and allied electrical works

100% Completed
 
Project Duration
Stipulated Date of Commencement January 21 2019
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,283,986.50
Awarded for ₹ 7,900,444.46

Project highlights

Power supply for High Court Complex

 
Contractors
Contractors
M/s. Consistent Engineers
Consultants
Consultants
4

Deep Cleaning and Housekeeping Work

100% Completed
 
Project Duration
Stipulated Date of Commencement January 29 2021
Actual Date of Completion November 30 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,193,470.00
Awarded for ₹ 39,593,350.00

Project highlights

Deep clenaing and housekeeping services for new High Court Building

 
Contractors
Contractors
M/s. Ecoclean System and solutions
Consultants
Consultants
M/s LKS India Pvt. Ltd.
5

Supply, Installation, Testing & Commissioning of Bio Digester Plant

100% Completed
 
Project Duration
Stipulated Date of Commencement February 21 2021
Actual Date of Completion December 08 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,832,140.00
Awarded for ₹ 1,832,000.00

Project highlights

Installtion of Bio Digester Plant for treating kitchen waste from building and for generation of bio gas that will be again used in kitchen for cooking purpose.

 
Contractors
Contractors
M/s. Urja Bio System Pvt. Ltd.
Consultants
Consultants
M/s LKS India Pvt. Ltd.
6

Construction of New High Court Complex at Penha De France, Porvorim, Goa- S.H: Laying of water supply pipeline for permanent connection

100% Completed
 
Project Duration
Stipulated Date of Commencement December 06 2020
Actual Date of Completion April 30 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,363,835.00
Awarded for ₹ 7,155,597.00

Project highlights

Laying of water supply pieline for new high Court Complex from Atal Setu approach near Hero Showroom.

 
Contractors
Contractors
M/s. Wibro Construction Co. Pvt. Ltd.,
Consultants
Consultants
M/s LKS India Pvt. Ltd.
Similar Projects

See Similar Projects

Similar Project

False ceiling work.

View Details
Similar Project

Renovation of Office Premises occupied by the Goa Public Service Commission, EDC House, Panaji

View Details
Similar Project

Design, Supply, Installation and commissioning of seed processing machinery with capcity of 2 tonnes per hour for paddy or 4 tonnes per hour for wheat at Ella, Old Goa.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.