Project Duration
Actual Date of Completion April 30 2013
Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 20 sub works. The details of the same available below

1

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works

Completed
 
Project Duration
Stipulated Date of Commencement December 21 2007
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 573,453,985.00
Awarded for ₹ 734,634,449.00

Project highlights

Basement + Ground + 5 RCC framed structure

 
Contractors
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2

Lift work

Completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Actual Date of Completion March 05 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,729,540.00
Awarded for ₹ 27,700,000.00
 
Contractors
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3

External Electrical works.

Completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Actual Date of Completion March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,33,96,780.00
Awarded for ₹ 21,149,474.00
 
Contractors
Contractors
M/s. Imperial Engineering Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4

Air conditioning works.

Completed
 
Project Duration
Stipulated Date of Commencement June 16 2011
Actual Date of Completion March 25 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,57,17,757.00
Awarded for ₹ 23,604,023.00
 
Contractors
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

Completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Actual Date of Completion February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,27,37,030.00
Awarded for ₹ 9,146,323.00
 
Contractors
Contractors
M/s. Eagle Construction Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6

Audio Visual Equipments for conference system and AV room

Completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Actual Date of Completion April 24 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,34,15,719.00
Awarded for ₹ 13,448,394.00
 
Contractors
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7

Telephone Exchange and UPS (Part A- UPS work)

Completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Actual Date of Completion March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,92,891.00
Awarded for ₹ 4,693,205.00
 
Contractors
Contractors
M/s. Imperial Engineering Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8

Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)

Completed
 
Project Duration
Stipulated Date of Commencement February 01 2012
Actual Date of Completion March 16 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,00,26,362.00
Awarded for ₹ 5,637,190.00
 
Contractors
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9

Decorative Glazing for staircase blocks.

Completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Actual Date of Completion March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 87,89,272.80
Awarded for ₹ 8,250,144.00

Project highlights

Decorative Glazing works

 
Contractors
Contractors
M/s. R. S. Lawande
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10

Carpentry and interior work.

Completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Actual Date of Completion March 26 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,96,84,461.30
Awarded for ₹ 53,022,057.00

Project highlights

Carpentry works

 
Contractors
Contractors
M/s.Concept Creator
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11

Readymade furniture works

Completed
 
Project Duration
Stipulated Date of Commencement July 09 2012
Actual Date of Completion May 27 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,28,94,732.00
Awarded for ₹ 37,798,417.00

Project highlights

Readymade Furniture works

 
Contractors
Contractors
M/s. Durian Industries Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12

Internal, external and special lighting fixtures (Part B : External lights and façade lighting)

Completed
 
Project Duration
Stipulated Date of Commencement August 11 2012
Actual Date of Completion March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,09,68,986.00
Awarded for ₹ 6,849,960.00
 
Contractors
Contractors
M/s. Shanti Electrical Enterprises Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13

Supply of trees, grass, grass covers & allied material for landscaping works.

Completed
 
Project Duration
Stipulated Date of Commencement January 17 2013
Actual Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,02,563.00
Awarded for ₹ 2,983,810.00

Project highlights

Landscaping works

 
Contractors
Contractors
M/s. Vrindavan Agricultural Services
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14

Signages work

Completed
 
Project Duration
Stipulated Date of Commencement January 27 2013
Actual Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,59,583.00
Awarded for ₹ 4,023,779.00

Project highlights

Signages works

 
Contractors
Contractors
M/s. Harshada Trading Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15

Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works

Completed
 
Project Duration
Stipulated Date of Commencement January 31 2013
Actual Date of Completion February 02 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,228,580.00
Awarded for ₹ 16,956,091.00
 
Contractors
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16

CPOE switches

Completed
 
Project Duration
Stipulated Date of Commencement April 12 2012
Actual Date of Completion January 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ ----
Awarded for ₹ 1,539,900.00
 
Contractors
Contractors
M/s. AGC Networks Limited
Consultants
Consultants
In-house (GSIDC)
17

Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.

Completed
 
Project Duration
Stipulated Date of Commencement October 12 2013
Actual Date of Completion December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,321,131.00
Awarded for ₹ 2,375,201.00

Project highlights

Compactors in Record rooms

 
Contractors
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
Consultants
In-house (GSIDC)
18

Raising the Existing Compound Wall and Providing Additional Gutters

Completed
 
Project Duration
Stipulated Date of Commencement October 16 2013
Actual Date of Completion March 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,002,100.00
Awarded for ₹ 4,991,914.50

Project highlights

Additional gutters & Compound wall works

 
Contractors
Contractors
M/s. A. Ponnuraj
Consultants
Consultants
In-house (GSIDC)
19

– Additional Miscellaneous work.

Completed
 
Project Duration
Stipulated Date of Commencement January 23 2015
Actual Date of Completion November 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,853,393.00
Awarded for ₹ 13,328,661.00

Project highlights

Additional furniture & minor civil works.

 
Contractors
Contractors
M/s. Concept Creators
Consultants
Consultants
M/s. Nitin Arolkar
20

Supply, installation, testing & commissioning of C1287 RMU

Completed
 
Project Duration
Stipulated Date of Commencement April 23 2018
Actual Date of Completion July 01 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,690,000.00
Awarded for ₹ 2,645,220.00
 
Contractors
Contractors
M/s. Pristine Engineering Services
Consultants
Consultants
In-house (GSIDC)
Similar Projects

See Similar Projects

Similar Project

External development works.

View Details
Similar Project

Construction of new building for SCERT at Porvorim, Goa – Miscellaneous HT Tapping works

View Details
Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim-Goa – Landscaping works

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.