Project Duration
Stipulated Date of Commencement
July 29 2008
Actual Date of Completion
July 13 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,614,408.61
Awarded for
₹ 22,424,910.00
Project highlights
False ceiling, reception counters, work table counters, modular furniture items for library such as book racks, tables, work stations etc.
Contractors
M/s. Concept Creators
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.