Project Duration
Stipulated Date of Commencement
March 25 2013
Actual Date of Completion
May 24 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,322,882.00
Awarded for
₹ 1,298,711.00
Project highlights
CCTV works for Ravindra Bhavan
Contractors
M/s. Reconnoitre systems.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.