Project Duration
Stipulated Date of Commencement
June 12 2012
Actual Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,839,786.00
Awarded for
₹ 6,220,033.00
Project highlights
Providing of structural work like catwalk, in the building
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.