Project Duration
Stipulated Date of Commencement
November 15 2014
Actual Date of Completion
January 04 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,495,463.00
Awarded for
₹ 41,804,375.00
Project highlights
Provision of temporary hangers as accomodation for pilgrims, and other arrangments to ensure smooth functioning of Exposition of relics of St. Francis Xavier.
Contractors
M/s.Purple Focus Pvt. Ltd.
Consultants
In-house (GSIDC)