Project Duration
Stipulated Date of Commencement
January 09 2015
Actual Date of Completion
March 16 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 884,746.00
Awarded for
₹ 885,000.00
Project highlights
Demolition of existing deteriorated jetty.
Contractors
M/s. Kamat Equipments Services
Consultants
M/s. Kashec Engineers Pvt. Ltd.