Project Duration
Stipulated Date of Commencement April 07 2017
Actual Date of Completion December 18 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,878,576.00
Awarded for ₹ 20,699,311.00

Project highlights

The project is having fully ventilated processing unit, office, security room, truck cleaning bay, leached tank, weighbridge facility etc. All internal road and processing area is made of concrete (VDF Floor).

 
Gallery Image
Contractors
M/s.Rakesh Kambli
Gallery Image
Consultants
M/s.Rahul Deshpande (Pre-tender)/ M/s.Manoj Amshekar (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of RMU

View Details
Similar Project

Construction of Yojana Bhavan for Directorate of Planning, Statistics and Evaluation at Porvorim, Goa

View Details
Similar Project

Electrical works.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.