Status
100%
Completed

Project highlights

Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations

 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 6 sub works. The details of the same available below

1

Panaji to Patradevi (Part I) – Chainage 0.00 km. to 21.90 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement March 21 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 853,639.00
Awarded for ₹ 840,171.60
 
Contractors
Contractors
M/s.Rakesh Kambli
Consultants
Consultants
In-house (GSIDC)
2

Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement March 21 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 853,639.00
Awarded for ₹ 840,171.60
 
Contractors
Contractors
M/s.Rakesh Kambli
Consultants
Consultants
In-house (GSIDC)
3

Panaji to Pollem (Part I) – Chainage 0.00 km. to 31.30 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement April 01 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,280,289.25
 
Contractors
Contractors
M/s.H. Candolcar & Sons
Consultants
Consultants
In-house (GSIDC)
4

Panaji to Pollem (Part II) – Chainage 31.30 km. to 62.60 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement April 01 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,157,599.20
 
Contractors
Contractors
M/s. Gaurish P. Naik
Consultants
Consultants
In-house (GSIDC)
5

Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement April 16 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,123,044.00
 
Contractors
Contractors
M/s. Veejay Facility Management Ltd.
Consultants
Consultants
In-house (GSIDC)
6

Cortalim to Verna via Airport – 24.00 km.

100% Completed
 
Project Duration
Stipulated Date of Commencement April 16 2013
Actual Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 935,546.00
Awarded for ₹ 880,992.00
 
Contractors
Contractors
M/s. Veejay Facility Management Ltd.
Consultants
Consultants
In-house (GSIDC)
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing & Commissioning of Bio Digester Plant

View Details
Similar Project

Lifts / Elevator work.

View Details
Similar Project

Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.