Status
Completed
Contractors
Consultants
Sub Works
This project involved 3 sub works. The details of the same available below
1
S.H. Carriage of Water
Completed
Project Duration
Stipulated Date of Commencement
November 12 2013
Actual Date of Completion
April 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,025,750.00
Awarded for
₹ 2,044,000.00
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)
2
S.H. Carriage of Water
Completed
Project Duration
Stipulated Date of Commencement
June 19 2017
Actual Date of Completion
August 18 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,115,875.00
Awarded for
₹ 8,619,018.75
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Pedro Gomes
Consultants
In-house (GSIDC)
3
S.H. Carriage of Water for 3 years
Completed
Project Duration
Stipulated Date of Commencement
October 01 2018
Actual Date of Completion
March 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,347,625.00
Awarded for
₹ 25,844,737.50
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Pedro Gomes
Consultants
In-house (GSIDC)
See Similar Projects
Steel Operation Theatre.
View Details
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.
View Details
Supply, installation, testing and commissioning of 15 passenger cum bed lift for T. B. and chest diseases hospital, St. Inez, Goa.
View Details