Project Duration
Stipulated Date of Commencement
June 15 2006
Actual Date of Completion
October 16 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,834,633.00
Awarded for
₹ 42,696,401.00
Project highlights
Central air conditioning for Ward Block and other buildings at GMC, Bambolim.
Contractors
M/s. Voltas Limited
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Central Sterile Supply Department.
View Details
Furniture / Interior works.
View Details
Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS
View Details