Project Duration
Stipulated Date of Commencement January 17 2014
Actual Date of Completion March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,800,000.00
Awarded for ₹ 5,201,200.00
 
Gallery Image
Contractors
M/S. WIPRO GE HEALTHCARE PVT. LTD
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Interior, Furniture works

View Details
Similar Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Dialysis Machine

View Details
Similar Project

Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.