Project Duration
Stipulated Date of Commencement September 29 2013
Actual Date of Completion August 14 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 145,763,468.00
Awarded for ₹ 158,936,223.00

Project highlights

• Total built-up area = 3610.63 sq. m.
• Ground Floor : Admin office, staff, etc.
• First Floor : 2 lecture halls.
• Second Floor : 1 lecture hall.
• Other facilities such as lift, fire fighting, HVAC, seat & desk with
self opening & closing system.

 
Gallery Image
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Furniture and Acoustical work.

100% Completed
 
Project Duration
Stipulated Date of Commencement May 22 2015
Actual Date of Completion August 14 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,386,310.00
Awarded for ₹ 10,777,777.00
 
Contractors
Contractors
M/s. Harshada Trading Company
Consultants
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Similar Projects

See Similar Projects

Similar Project

Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.

View Details
Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Details
Similar Project

Lift work.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.