Project Duration
Stipulated Date of Commencement
June 17 2006
Actual Date of Completion
October 14 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 118,993,540.00
Awarded for
₹ 135,678,880.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 2 sub works. The details of the same available below
1
Furniture works
100% Completed
Project Duration
Stipulated Date of Commencement
February 23 2008
Actual Date of Completion
June 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
Providing of split air conditioners.
100% Completed
Project Duration
Stipulated Date of Commencement
October 23 2008
Actual Date of Completion
November 06 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 726,404.00
Awarded for
₹ 762,190.00
Contractors
M/s. Blue Star Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Hospicio Hospital at Margao.
View Details
Purchase of medical machinery & equipment for Upgraded 100 bedded ESI hospital at Margao -sh Supply, installation, testing and commissioning of Radiology & Imaging rquipment (2nd call)
View Details
Surveillance & Audio Video System.
View Details