Project Duration
Stipulated Date of Commencement July 15 2004
Actual Date of Completion April 30 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 140,325,985.00
Awarded for ₹ 147,280,036.00
 
Gallery Image
Contractors
M/s. Nagarjuna Construction Company Ltd
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 

Sub Works

This project involved 3 sub works. The details of the same available below

1

Supply, Installation, Testing and Commissioning of Medical Gas Pipelines.

100% Completed
 
Project Duration
Stipulated Date of Commencement October 26 2006
Actual Date of Completion July 31 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,119,623.00
Awarded for ₹ 11,376,000.00
 
Contractors
Contractors
M/s. BOC India Limited
Consultants
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
2

Furniture and miscellaneous work.

100% Completed
 
Project Duration
Stipulated Date of Commencement January 05 2007
Actual Date of Completion June 30 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,264,548.25
Awarded for ₹ 22,590,380.00
 
Contractors
Contractors
M/s. Concept Creators
Consultants
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
3

Hospital furniture work.

100% Completed
 
Project Duration
Stipulated Date of Commencement June 27 2008
Actual Date of Completion December 17 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,370,852.00
Awarded for ₹ 15,401,378.00
 
Contractors
Contractors
M/s. Royal Safe Company
Consultants
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa S.H.: Supply, Installation, Testing & Commissioning of 500KVA DG set at North Goa District Hospital, Mapusa

View Details
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa S.H.: Maintenance Contract for the UPS systems installed at Upgraded Cottage Hospital, Chicalim for a period of three years (2019-2022)

View Details
Similar Project

Supply, Testing and Commissioning of Suction machine

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.