This project involved 3 sub works. The details of the same available below
1
Maintenance of college garden at Goa Dental College and Hospital
Completed
Project Duration
Stipulated Date of Commencement
March 03 2014
Actual Date of Completion
February 09 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,89,670.00
Awarded for
₹ 10,34,205.00
Project highlights
Maintenance of landscaping works at Goa Dental College.
Contractors
M/s. Limboo Softscape,
Consultants
In-house (GSIDC)
2
SH – Maintenance of landscaping works at Goa Medical College….
Completed
Project Duration
Stipulated Date of Commencement
January 02 2014
Actual Date of Completion
May 31 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,465,719.00
Awarded for
₹ 2,584,047.00
Project highlights
Maintenance of landscaping works at Goa Medical College.
Contractors
M/s. Limboo Softscape,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.,
3
SH- Premonsoon works
Completed
Project Duration
Stipulated Date of Commencement
July 07 2013
Actual Date of Completion
August 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,12,103.00
Awarded for
₹ 21,94,753.54
Project highlights
Premonsoon works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.,
See Similar Projects
Supply, Installation, Testing and Commissioning of Cardiac Monitors, ECG machine, Defribrillators, etc.
View Details
Civil works
View Details
Upgradation of Cansaulim Primary Health Centre (PHC) in Cortalim Constituency
View Details