Project Duration
Stipulated Date of Commencement December 27 2015
Actual Date of Completion April 30 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 834,975,942.53
Awarded for ₹ 996,008,692.20

Project highlights

Main Building
Basement:
• CSO (Central Stores office) & Pharmacy store
• Laundry, Stores &maintenance workshops & Parking space
Ground Floor:
• 21 OPD Clinics, Casualty with minor Operation Theatre,
• Diagnostics, Imaging suite, Physiotherapy, Blood Bank, Laboratory
• CSSD (Central Supply Stores Department), IPD Kitchen etc.
First Floor:
• 7 Operation Theatres with Pre & Post-Operative Room, Surgery, ENT IPD ward, Burns ward, Prisoners’ ward etc.
Second Floor:
• Administrative block, 3 OT, Obstetrics & Gynecology and Pediatric IPD wards, NICU (Neonatal Intensive Care Unit), PICU (Pediatric Intensive Care Unit)
Third Floor:
• MICU, ICU, Dialysis, Psychiatry, Medicine, IPD wards
Mortuary Building
• Morgue for 72 cabinets, Autopsy Room, Embalming Room, Waiting, Doctors Rooms, Post Mortem Room etc.
Utility Building
• Transformers, Electrical panel room Chiller system, Water Filtration system, Hot water tanks
• Underground water tanks for raw water, domestic water, soft water and fire water.
• D. G. sets outside

 
Gallery Image
Contractors
M/s. Parnika Commercial & Estates P. Ltd
Gallery Image
Consultants
M/s. KICONS Limited
 

Sub Works

This project involved 11 sub works. The details of the same available below

1

False ceiling work.

100% Completed
 
Project Duration
Stipulated Date of Commencement December 30 2016
Actual Date of Completion April 15 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 69,812,937.00
Awarded for ₹ 60,183,352.75

Project highlights

Metal False Ceiling, Calcium silicate false ceiling work

 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s. KICONS Limited
2

Interior work

100% Completed
 
Project Duration
Stipulated Date of Commencement May 31 2018
Actual Date of Completion June 15 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 95,573,993.00
Awarded for ₹ 82,304,576.29

Project highlights

Modular, carpentry & miscellaneous furniture

 
Contractors
Contractors
M/s. T. S. Mistry,
Consultants
Consultants
M/s. KICONS Limited
3

Sewage Treatment Plant

100% Completed
 
Project Duration
Stipulated Date of Commencement April 01 2018
Actual Date of Completion April 30 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,972,974.00
Awarded for ₹ 23,053,800.00

Project highlights

0.4 MLD STP & RO Plant

 
Contractors
Contractors
M/s. Brisanzia Technologies Pvt. Ltd.
Consultants
Consultants
M/s. KICONS Limited
4

Supply, Installation, Testing & Commissioning of Central Sterile Supply Department (CSSD) equipments

100% Completed
 
Project Duration
Stipulated Date of Commencement November 12 2018
Actual Date of Completion May 11 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 33,054,427.00
Awarded for ₹ 26,606,001.00

Project highlights

The Project consist of supply and installation of variour Central sterile service equipments and furniture etc

 
Contractors
Contractors
M/s. Steris India Pvt.Ltd
Consultants
Consultants
M/s. KICONS Limited
5

SITC of medical gas supply system (MGSS)

100% Completed
 
Project Duration
Stipulated Date of Commencement January 03 2019
Actual Date of Completion October 24 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 47,193,574.50
Awarded for ₹ 62,030,298.77

Project highlights

The project consist of supply and erection of new medical gas line distribution system such as Oxygen Manifold system, Air compressors, Vaccumm Plant etc

 
Contractors
Contractors
M/s. Prenit World LLP
Consultants
Consultants
M/s. KICONS Limited
6

Rear Side parking and Biomedical Waste Building

100% Completed
 
Project Duration
Stipulated Date of Commencement April 15 2022
Actual Date of Completion December 14 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 32,678,364.00
Awarded for ₹ 36,058,328.56

Project highlights

Development of parking space

 
Contractors
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
Consultants
M/s. KICONS Limited
7

Supply & Installation of Lead Doors & Lead Glass

100% Completed
 
Project Duration
Stipulated Date of Commencement February 14 2020
Actual Date of Completion September 07 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,859,392.72
Awarded for ₹ 1,997,827.88

Project highlights

Supply and installation of lead doors

 
Contractors
Contractors
M/s. Manup Infrastructures
Consultants
Consultants
M/s. KICONS Limited
8

Supply, Installation, Testing and Commissioning of Token System

100% Completed
 
Project Duration
Stipulated Date of Commencement September 02 2019
Actual Date of Completion December 15 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,350,459.00
Awarded for ₹ 2,256,449.00
 
Contractors
Contractors
M/s. Geeta Automation Technologies
Consultants
Consultants
M/s. KICONS Limited
9

Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS

100% Completed
 
Project Duration
Stipulated Date of Commencement May 28 2020
Actual Date of Completion August 14 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 850,000.00
Awarded for ₹ 698,000.00
 
Contractors
Contractors
M/s. Techser Power Solutions Pvt Ltd
Consultants
Consultants
M/s. KICONS Limited
10

Steel Operation Theatre

100% Completed
 
Project Duration
Stipulated Date of Commencement August 19 2018
Actual Date of Completion February 22 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 73,754,252.00
Awarded for ₹ 72,280,905.00
 
Contractors
Contractors
M/s. Mediconz International
Consultants
Consultants
M/s. KICONS Limited
11

Construction of 500 Bedded District Hospital At Margao, Goa – LV System

100% Completed
 
Project Duration
Stipulated Date of Commencement November 09 2017
Actual Date of Completion March 31 2024
Status
100%
Completed
Cost (₹)
Estimated at ₹ 41,902,954.49
Awarded for ₹ 39,462,508.00

Project highlights

The work consists of Nurse Call system, telephone system, UPS, Building Management System, LAN, CCTV, etc.

 
Contractors
Contractors
M/s. Nupur Technologies Pvt. Ltd
Consultants
Consultants
M/s. KICONS Limited
Similar Projects

See Similar Projects

Similar Project

Hospital furniture work.

View Details
Similar Project

Construction of 450 bedded Ward Block at GMC Complex, Bambolim, Goa. Civil, Plumbing, Electrical and Fire Fighting work.

View Details
Similar Project

Lifts.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.