Project Duration
Stipulated Date of Commencement
February 07 2015
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,480,851.00
Awarded for
₹ 97,176,913.14
Project highlights
Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.
Contractors
M/s. shilpi Constructions
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.