Project Duration
Stipulated Date of Commencement
October 31 2009
Actual Date of Completion
February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,966,150.00
Awarded for
₹ 44,452,529.30
Contractors
M/s. M. V. Khandeparkar, M/s. M. V. Khandeparkar
Consultants
M/s. Keni & D’Souza, M/s. Keni & D’Souza
Sub Works
This project involved 4 sub works. The details of the same available below
1
Electrical work.
100% Completed
Project Duration
Stipulated Date of Commencement
June 15 2011
Actual Date of Completion
August 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,609,226.00
Awarded for
₹ 6,841,664.00
Contractors
M/s. Power & Instrumentation (Guj) Ltd.
Consultants
M/s. Keni & D’Souza
2
False ceiling work.
100% Completed
Project Duration
Stipulated Date of Commencement
November 03 2011
Actual Date of Completion
February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,387,133.00
Awarded for
₹ 2,011,550.00
Contractors
M/s. Concept Creators
Consultants
M/s. Keni & D’Souza
3
Readymade furniture & signages.
100% Completed
Project Duration
Stipulated Date of Commencement
June 28 2012
Actual Date of Completion
February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,408,454.00
Awarded for
₹ 3,977,777.00
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Keni & D’Souza
4
Road works (concrete and paver) and landscaping works
100% Completed
Project Duration
Stipulated Date of Commencement
November 03 2013
Actual Date of Completion
March 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,83,67,542.89
Awarded for
₹ 2,90,79,932.40
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Keni & D’Souza
See Similar Projects
Construction of Sewage Treatment Plant including sewage network at Institute of Psychiatry & Human Behaviour complex at Bambolim, Goa -Construction of building and sewage pipeline work
View Details
Supply, Testing and Commissioning of Anaesthesia Workstation
View Details
Face-lift to Tisk Usgao Hospital building including staff quarters
View Details