Project Duration
Stipulated Date of Commencement
March 03 2007
Actual Date of Completion
December 19 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,969,028.00
Awarded for
₹ 186,209,408.98
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC
View Details
Supply, Testing and Commissioning of Intra Aortic Balloon Pumps
View Details
SITC of medical gas supply system (MGSS)
View Details