Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Civil, Plumbing & Electrical works.
Completed
Project Duration
Stipulated Date of Commencement
December 27 2013
Actual Date of Completion
January 20 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,214,248.00
Awarded for
₹ 85,526,271.00
Contractors
M/s. R. B. S. Candiaparcar
Consultants
M/s. Datta Kare Associates
2
Furniture work.
Completed
Project Duration
Stipulated Date of Commencement
February 27 2015
Actual Date of Completion
December 20 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,323,598.00
Awarded for
₹ 6,353,797.50
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Fire Fighting work
View Details
Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa -(Canacona taluka)- GHS Khotigao
View Details
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka – Package H (G.P.S Kharekhajan- Virdi, G.P.S Kudchire, G.P.S. Pratap Nagar- Harvalem, G.H.S. Late Jayendra J. Rane- Kudchire)
View Details