Project Duration
Stipulated Date of Commencement
September 24 2006
Actual Date of Completion
March 08 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,659,445.00
Awarded for
₹ 5,977,351.00
Project highlights
Extension work of school building
Contractors
M/s. M.B. Kinlekar, M/s. M.B. Kinlekar
Consultants
M/s. Effective Architectural Services
Sub Works
This project involved 1 sub works. The details of the same available below
1
Extension of H. B. Desai Government High School at Thane in Sattari Taluka – Additional work of 4 classrooms, laboratory, compound wall, store room & hall.
100% Completed
Project Duration
Stipulated Date of Commencement
December 18 2009
Actual Date of Completion
February 17 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,376,099.00
Awarded for
₹ 8,679,690.00
Project highlights
Construction of additional 4 classrooms, laboratory, compound wall, store room, hall along with painting and electrification works.
Contractors
M/s. K. G. Thomas
Consultants
M/s. Effective Architectural Services
See Similar Projects
Developemet of village school playground at anandwadi in Sanguem Taluka.
View Details
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Details
Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package C (Sattari Taluka) – (GPS Paikul, GPS Maigini, GPS Malpan, GPS Dhada Melauli, GPS Shel Melauli)
View Details