Project Duration
Stipulated Date of Commencement
May 23 2013
Actual Date of Completion
October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,265,380.00
Awarded for
₹ 7,015,854.00
Project highlights
School Building with 4 classrooms of international size 60 sq. m
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Datta Kare Associates
See Similar Projects
Repairs/upgradation & maintenance of Govt. schools in the State of Goa – Sattari Taluka: Package M- (GPS Saleli, GPMS Velgem, GPS Mauxi, GHS Shelop Khud, GPS Dabos)
View Details
Reconstruction of Government High School at Betoda, Goa.
View Details
Repairs/ upgradation & maintenance of Government School in the State of Goa – GHS Daushire
View Details





