Project Duration
Stipulated Date of Commencement
September 01 2006
Actual Date of Completion
May 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,777,629.00
Awarded for
₹ 1,798,714.00
Project highlights
The building consists of 2 classrooms, staff room, toilets, etc.
Contractors
M/s. Sharadchandra H. Katkar
Consultants
M/s. Effective Architectural Services