Project Duration
Stipulated Date of Commencement
February 13 2019
Actual Date of Completion
September 30 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,586,617.00
Awarded for
₹ 11,838,449.94
Contractors
M/s. Crystal Ball
Consultants
M/s. Bhaskar Wagle and Associates.