Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Civil, Plumbing & Electrical works.

Completed
 
Project Duration
Stipulated Date of Commencement January 06 2009
Actual Date of Completion April 20 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,31,78,550.00
Awarded for ₹ 76,513,097.00

Project highlights

The Panchayat Ghar is a G+1 RCC framed structure having shops, Bank, Post Office, Toilet for ladies and gents on the Ground floor. The first floor complrises of a Community Hall with a capaity of 400 seats with dining area, green rooms for ladies and gents, Office for Panchayat, Gymnasium, Library. Toilet for ladies and gents etc.

 
Contractors
Contractors
M/s. Acron Developers Pvt. Ltd.
Consultants
Consultants
M/s. Vijaykumar Sawant Associates
2

Phase I : Land Development.

Completed
 
Project Duration
Stipulated Date of Commencement February 22 2008
Actual Date of Completion August 01 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,780,533.00
Awarded for ₹ 9,700,990.00

Project highlights

Land filling and construction of retaining wall

 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Vijaykumar Sawant Associates
Similar Projects

See Similar Projects

Similar Project

Upgradation of Outlet of Goa State Horticulture Corporation Ltd. at Altinho to the standard of Modern super market.

View Details
Similar Project

Supply, Installation, Testing and Commissioning of Server and Networking Equipment.

View Details
Similar Project

Additional furniture items.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.