Project Duration
Stipulated Date of Commencement February 22 2014
Actual Date of Completion May 27 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 41,744,302.00
Awarded for ₹ 42,575,717.00

Project highlights

Internal Roads of total approximate length of 3.4 km hotmixed and widened at certain locations.

 
Gallery Image
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji

View Details
Similar Project

Hot mixing & Improvement of Internal Roads in V. P. St. Jose de Areal in Velim Constituency.

View Details
Similar Project

Widening of roads and relocation of structures in Fatorda Constituency- Phase I

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.