Project Duration
Stipulated Date of Commencement
May 26 2006
Actual Date of Completion
May 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 30,931,800.00
Awarded for
₹ 38,560,191.50
Project highlights
Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, providing gutters and cross drainages wherever required. The approximate length of the road is around 10.10 Kms.
Contractors
M/s.Madanant Construction Pvt. Ltd
Consultants
M/s.Keni & D’Souza