Project Duration
Stipulated Date of Commencement
January 11 2019
Actual Date of Completion
February 28 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 89,868,697.00
Awarded for
₹ 77,898,390.56
Project highlights
The total length of the road is 2.473 km and work involved widening & hotmixing, paved pathway with seating.
Contractors
M/s. Ritesh Developers
Consultants
M/s. Vijaykumar Sawant, And Associates