Project Duration
Stipulated Date of Commencement
April 26 2007
Actual Date of Completion
October 08 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,644,386.00
Awarded for
₹ 34,552,373.00
Contractors
M/s. Kirloskar Constructions & Engineers Limited
Consultants
M/s. Construma Consultancy Pvt. Ltd.
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of Jetty at Brittona – Additional works.
100% Completed
Project Duration
Stipulated Date of Commencement
July 16 2010
Actual Date of Completion
January 10 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,985,905.00
Awarded for
₹ 2,183,970.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Vijaykumar Sawant Associates
2
Construction of Jetty at Brittona – Additional electrical works
100% Completed
Project Duration
Stipulated Date of Commencement
April 06 2010
Actual Date of Completion
September 21 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 609,064.00
Awarded for
₹ 651,172.00
Contractors
M/s. Oman Enterprises
Consultants
In-house (GSIDC)
See Similar Projects
Hotmiixing of road in Fatorda for Lusofonia Games
View Details
Widening of road in Calangute – Baga.
View Details
Comprehensive electrical underground cabling work at Bambolim.
View Details





