Project Duration
Stipulated Date of Commencement December 29 2021
Actual Date of Completion June 03 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 121,210,152.00
Awarded for ₹ 119,829,470.55

Project highlights

Bridge consists of span arrangement 42.5m x 2 Nos.= 85 mts Foundation-Pile foundation of 1.2m dia & length 25m are proposed. Pile foundation will be in M35 concrete with 8mm liners. Pile caps will be supported on piles. Sub structure comprises of RCC plate piers, RCC pier cap with pier pedestals. Grade of concrete shall be M35. Superstructure comprises of composite steel concrete construction. RCC deck slab is supported on steel work spanning between piers. Steel work comprises of plate girders for 42.5m span. Length of Approache roads : 156m (Melauli Side) & 105m (Paikul Side).

 
Gallery Image
Contractors
M/s. Surabhi Counstructions
Gallery Image
Consultants
M/s. Vijay Kumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.

View Details
Similar Project

Bridge Across St. Inez Creek on 18th June Road, Panaji

View Details
Similar Project

Landscaping work.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.