Project Duration
Stipulated Date of Commencement
July 27 2014
Actual Date of Completion
January 09 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,550,000,000.00
Awarded for
₹ 4,030,000,000.00
Project highlights
Bridge connecting Panaji and Porvorim of total lenght 5.44 km with cable stayed portion in the river spanning to 620m..
Contractors
M/s. Larsen & Toubro Limited
Consultants
M/s. TPF Engineering Pvt. Ltd.