Project Duration
Stipulated Date of Commencement
April 23 2016
Actual Date of Completion
April 05 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 236,470,437.00
Awarded for
₹ 242,441,097.11
Project highlights
Cfonstruction of 2 Lane Bridge with approaches.

Contractors
M/s. Larsen & Toubro Ltd.

Consultants
M/s. Rahul Deshpande
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable
100% Completed
Project Duration
Stipulated Date of Commencement
November 29 2017
Actual Date of Completion
December 02 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 253,495.00
Awarded for
₹ 276,450.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of 11 KV, 3C x 300 sq. mm, underground armored cable – 120 meters length.

Contractors
M/s. Pristine Engineering Services

Consultants
M/s. Rahul Deshpande
2
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 33 kV Overhead Lines
100% Completed
Project Duration
Stipulated Date of Commencement
January 17 2018
Actual Date of Completion
March 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 571,048.00
Awarded for
₹ 597,920.00
Project highlights
The scope of work includes dismantling of existing 33kV overhead lines and installation, testing & commissioning of 33 KV, 3C x 400 sq. mm, underground armored cable supplied by Goa Electricity Department.

Contractors
M/s. Pristine Engineering Services

Consultants
M/s. Rahul Deshpande

See Similar Projects

St. Inez Creek Barricading
View Details
Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona.
View Details
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) :-Civil works.
View Details