Project Duration
Stipulated Date of Commencement
August 27 2006
Actual Date of Completion
November 09 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 66,755,638.12
Awarded for
₹ 75,996,000.00
Project highlights
Length of bridge = 42 m with footpaths on either side. The total length of approaches is 850 m with one additional pier in the middle.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Construma Consultancy Pvt. Ltd.