Project Duration
Stipulated Date of Commencement
November 01 2004
Actual Date of Completion
June 21 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,434,621.00
Awarded for
₹ 17,783,313.00
Project highlights
• Length : 52 m.
• Three continuous spans with cast-in-situ R.C.C. T-beam superstructure.
• Carriageway 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Margao and Colva side.
• Electric poles with fixtures on the bridge and approaches.
Contractors
M/s. Naik Constructions
Consultants
M/s. M. V. S. Borcar & Associates