Project Duration
Stipulated Date of Commencement
February 16 2014
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 213,460,391.00
Awarded for
₹ 234,860,258.00
Project highlights
Construction of bus stand & market complex as there is no bus stand and proper market complex at present in Pernem city.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of bus stand & market complex at Pernem, Goa – Interior & Furniture Works
100% Completed
Project Duration
Stipulated Date of Commencement
December 06 2016
Actual Date of Completion
August 12 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,296,693.00
Awarded for
₹ 7,882,786.00
Project highlights
Interior Furniture Works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. UCJ Architecture & Environment
2
Construction of Bus Stand & Market Complex at Pernem – Erecting 11 kV overhead line from feeder at the Electricity Department Substation to the Bus Stand Substation
100% Completed
Project Duration
Stipulated Date of Commencement
April 18 2018
Actual Date of Completion
August 13 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,015,609.00
Awarded for
₹ 1,063,850.00
Project highlights
Work towards tapping HT power supply for the Bus Stand.
Contractors
M/s. Mauli Electricals
Consultants
M/s. UCJ Architecture & Environment
See Similar Projects
Hot mixing & Improvement of Road from Betul Bridge to Baradi Junction in Velim Constituency.
View Details
Construction of Jetty at Brittona – Additional works.
View Details
Construction of approaches to Cumbarjua bridge including road link upto Khandola college.
View Details